How Benton Harbor Replaced Lead Water Lines in a Fraction of the Time

In Simple Terms

Benton Harbor’s old water pipes could let lead get into drinking water. With public funding, several contractors working at once, and a coordinated effort to reach homes, the city checked or replaced most of its water lines in about a year. The work moved far faster than the usual 20-year timeline, though the final cost and exact number of pipes replaced remain unclear.

Short Pipes, Big Risks for Homes

Benton Harbor, Michigan, offers a striking example of how an infrastructure project can speed up when public funding, multiple contractors, and fewer administrative barriers come together. On November 2, 2022, the state said that 99% of the city’s water service lines had been inspected and that nearly 4,500 lines had either been replaced or confirmed to contain no lead. The emergency effort began in fall 2021, even though Michigan’s standard rules give communities as long as 20 years to replace lead lines.

A water service line connects the public water system to a property. It may run from a water main under the street all the way to a building. If any part of that line contains lead, the metal can enter the water under certain conditions. So a safe main water network is not enough: officials must identify the materials in the pipes serving homes and address lines made of lead or other materials that need replacing.

The problem in Benton Harbor did not begin in 2021. According to local reports cited at the time, water samples had exceeded the accepted lead benchmark since 2018. Local officials had expected to follow the standard 20-year schedule and said that a lack of funding prevented them from removing thousands of lines more quickly. Mayor Marcus Muhammad noted that only dozens of pipes had been replaced by then, while thousands more were believed to need removal.

The difference between an old line and a replacement came down to the pipe material. Lines identified as lead or galvanized steel were replaced with copper pipes. Lines found to be made of materials that did not contain lead did not need replacing. That distinction matters when interpreting the reported totals: the number of lines addressed or checked is not the same as the number of excavations or new pipes installed.

Three Timelines, One Urgent Project

Michigan strengthened its rules on lead and copper in drinking water in 2018. Under the standard framework, communities must replace an amount equal to an average of 5% of their lead lines each year, which would theoretically complete the work in 20 years. But the required rate rises to 7% a year when lead levels exceed the action threshold, reducing the timeline to a little less than 15 years.

The higher rate applies under specific technical conditions; the presence of an old pipe alone does not trigger it. The Michigan Department of Environment, Great Lakes, and Energy, known as EGLE, says the requirement applies when lead levels remain above the threshold after appropriate corrosion-control treatment has been installed. The higher rate remains in effect until sample results fall below the benchmark in two consecutive monitoring periods. Lead levels are considered above the threshold when the 90th-percentile value exceeds 15 parts per billion.

Benton Harbor was facing another clock even before the emergency target was announced. On July 1, 2021, EGLE asked the city to remove 7% of its lead lines within 12 months. The agency says the rules did not technically require the city to meet that rate at the time, but it urged the faster pace as a proactive measure.

Then, on October 14, 2021, Governor Gretchen Whitmer ordered state resources to be coordinated around Benton Harbor’s water problem. The state announced a goal of replacing all lead lines within 18 months, or by around March 2023. The new round of work began during the week of November 8, 2021. The project, then, was not governed by just one deadline: the standard framework allowed 20 years, the earlier request called for a 7% replacement rate over 12 months, and the governor’s operational goal was to complete the work in 18 months.

Funding Changed What Was Possible

Before the new plan, local officials cited funding as one reason progress had been slow. On April 27, 2022, the state announced that its “Building Michigan Together” plan would direct $45 million to the city for infrastructure work, including lead water lines. But excavation had begun months before the plan was signed. EGLE’s funding page also lists an allocation of $45 million from American Rescue Plan Act funds. The available records do not establish whether the two announcements refer to the same money or to a single funding source, so it would be premature to treat them as two confirmed separate sums—or to assume that they definitely match.

Funding records list other money earmarked for the project: $10 million from the state’s general fund in the fiscal year 2022 budget, a $5,557,000 grant from the U.S. Environmental Protection Agency, and $3 million from the Clean Water State Revolving Fund for lead-line replacement. These figures show that more than one level of government contributed, but they do not provide a single final accounting of how much was actually spent from each source.

In May 2022, a project presentation from the Federal Reserve Bank of Chicago estimated that the work involved about 4,438 lead service lines, based on a figure dated May 19 of that year. It put the expected cost at as much as $33.2 million, or about $7,500 per line. Those were projections, not a published final bill. And the figure of 4,438 refers to lead lines targeted for replacement, while the state’s total of nearly 4,500 also includes lines that were checked and found not to contain lead.

Earlier estimates offer another glimpse of the financial uncertainty. The state’s funding page listed an initial total estimate of $30 million and an anticipated funding gap of $11.4 million before contracts were awarded. It said updated estimates were expected in early 2022. In November 2022, the Michigan Department of Health and Human Services described the project as being on budget, but the available records do not provide a consolidated final cost reconciliation. The estimate of $7,500 per line, therefore, remains a projection rather than a confirmed final figure.

Working in Parallel Made the Excavation Faster

Rather than hiring one company to work street by street, the city and state agencies designed a bidding process that allowed several contractors to work in designated areas at the same time. EGLE says this approach helped speed the removal of lead and galvanized-steel lines and was key to completing the work in less than 18 months. Dividing the city into work areas let different crews operate in parallel instead of waiting for each stage to finish before the next could begin.

By late April 2022, 33% of the lead lines had been replaced with copper, according to a state update. The crews were averaging 18 lines a day as the weather improved, the workforce grew, and the sixth and final contractor began work. On May 25, 2022, the Michigan Department of Health and Human Services reported that more than half of the lines had either been replaced or confirmed to be lead-free. At that point, six contractors were operating 15 crews, and the pace remained at an average of 18 lines a day.

By September 20, 2022, more than 90% of the lines had been inspected and either replaced or confirmed not to contain lead. The average reported at the time—six excavations a day—did not necessarily mean that six lines were being replaced every day. The update counted excavation work, not completed replacements. As the project neared its end, the distinction between the number of sites excavated and the number of lines actually removed became increasingly important: an announcement of progress alone does not reveal what happened to every individual line.

Getting Permission to Enter Properties Was Part of the Job

Crews could not reach the pipes from the street alone. The work required access to private properties, so the city needed permission from property owners. The Federal Reserve Bank of Chicago notes that a Michigan law passed in 2018 made the water system responsible for the cost of the portion of a line on a homeowner’s property once the owner agreed to the work. That arrangement addressed part of the financial burden, but it did not eliminate the need to contact each property and obtain permission to enter.

In February 2022, the city passed an ordinance requiring the replacement work to proceed while officials sought owners’ permission to enter, with fines of up to $500 for noncompliance. By November 2, 2022, about 2,800 right-of-entry forms had been completed among the city’s 2,900 active water customers. These figures refer to forms and customers, not to the number of pipes replaced. A form may be a procedural requirement for visiting a property, but on its own it does not show what inspection found or what happened to the line.

These details show that the project’s speed did not come from excavation alone. It also depended on funding to mobilize contractors, contracts that allowed work to happen simultaneously, and procedures for securing access to properties. The available account does not make it possible to measure precisely how much time each factor saved or how much each contributed. It does, however, show that the long timeline allowed by the rules was not an insurmountable technical limit.

What the Completion Rate Does—and Doesn’t—Tell Us

On November 2, 2022, the Michigan Department of Health and Human Services said nearly 4,500 lines had either been replaced or confirmed not to contain lead. The department described the campaign as five months ahead of schedule, with no direct cost to residents and within budget. Taken on its own, that announcement suggests the city completed most of a job in a little over a year—a task the standard framework could have allowed to stretch across two decades.

But a 99% completion rate does not mean that 99% of the pipes were dug up and replaced. The total combines two different outcomes: a lead or galvanized-steel line that was removed and replaced with copper, and a line that was inspected and found not to contain lead, so it did not need replacing. The available records do not break the overall figure down by those two categories. It is therefore not possible to infer the actual amount of excavation or the number of new copper pipes from the combined completion figure alone.

The claim that the project was “ahead of schedule” also depends on which deadline is used for comparison. Against the 18-month target, the November 2022 announcement put the project five months ahead. EGLE described the pace as more than 10 times faster than what the city was required to do under the rule it cited. But measured against the governor’s March 2023 target, the last known lead line was removed in May 2023—about two months late.

The Pipes Came Out—and Lead Measurements Improved

EGLE said the city’s last known lead service line was replaced in May 2023. Then, on June 8, 2023, the U.S. Environmental Protection Agency ended an order issued under the Safe Drinking Water Act, saying its requirements had been met and the city’s lead lines had been fully replaced. That development marks the completion of a crucial part of the infrastructure effort, but it does not remove the need to keep monitoring the water.

State data show how lead levels at the tap changed, using the 90th-percentile measure. Since the first exceedance in 2018, the reported values were 22, then 27, then 32, followed by 23, 24, 24, then 15, 14, 9, 1, and 1 parts per billion. Measurements first rose to a peak of 32, then declined in later readings, reaching 1 in the last two results in the published series. This measure should not be confused with the result of a single sample from one home: it summarizes the distribution of sample results in the way the state uses to compare lead levels with its benchmark.

The sequence offers another reason to view the project as a long-term process rather than a single completion announcement. Repeated exceedances in earlier years gave way to a clear decline in later readings as lines were replaced. But the figures alone cannot isolate the effect of each action or prove that excavation by itself caused every change. Continued sampling, alongside the infrastructure work, remains important for assessing water safety over time.

The Bottom Line

Benton Harbor shows that the timeline permitted by regulations does not necessarily determine how quickly work gets done. Michigan’s standard rules allowed 20 years to replace lead lines, but the city moved from a slow plan constrained by limited funding to a campaign drawing on state and federal resources, dividing the work among six contractors and 15 crews, and working to make property access easier. By November 2022, 99% of the lines had been checked, with contaminated lines replaced and others confirmed to be lead-free.

Still, the completion rate should not be mistaken for proof that every line counted was excavated and replaced: no published breakdown separates replacements from lines found not to contain lead. The estimated cost of $7,500 per line was a projection, not a published final accounting, even though officials described the project as staying within budget. Replacing the last known lead line in May 2023 and the EPA’s closure of its order in June marked the end of a major phase. The broader lesson is that funding, organization, and coordination can turn a long regulatory timeline into a much faster effort—but transparent final figures are essential to understanding exactly what was accomplished.